Current Roadway Maintenance - This page will be updated as projects are added. Start/completion dates are for general reference only and are subject to change.
Important Road Construction Notice: 🛣️
- Expect Delays, Lane Closures, and Construction Equipment in the Area
- For Chip Sealed Roads: Loose Gravel on the Road for at least One Month
👷We appreciate your patience as we work to improve your ROADS!
🚧Paving and Chip Seal Season: 🚧 Here is the tentative schedule below.
Week of June 15, 2026
| Paving | Westside Calispel Rd | MP 0.0-6.6 |
Week of June 22, 2026
| Paving | LeClerc Rd N | MP 16.1-29 |
Week of July 6, 2026
| Chip Sealing | Tweedie Rd | MP 0.0-1.6 |
| Chip Sealing | Green Rd | MP 1.1-2.4 |
Week of July 13, 2026
| Chip Sealing | Westside Calispel Rd | MP 0.0-6.6 |
🛑Chips will be on the road for longer than one month.🛑
Possible WSDOT Closure on Hwy 211, traffic diversion on Westside Calispel Rd.
Week of July 20, 2026
| Paving (finishing up) | LeClerc Rd N | MP 16.1-29 |